- Home
- >
- Tender
- >
- Himachal Pradesh Tender
- >
- Department of HIMACHAL PRADESH STATE ELECTRICITY BOARD
- >
NTID 44556550
ProcXpert
Share Your purchase requirement, Our ProcXpert team will Connect you to right Supplier.
Inquiry NowCorrigendum Replacement Of D in Kinnaur - Complete Tender Details
Find eligibility criteria, important deadlines, bidding requirements, and download official documents for "Corrigendum Replacement Of D" in Kinnaur, India.
HIMACHAL PRADESH STATE ELECTRICITY BOARD
Kinnaur, Himachal Pradesh, India
NTID 44556550
- Opening Date : Mon 30th March, 2026
- Closing Date : Mon 30th March, 2026
- ₹ 310340.00
- NTID 44556550
Tender Description
Documents
Get Complete Tender Details Now - Download the Document!
Download Now – Only ₹200-
Document-1
721.3 kBOil_India_ExtraDoc...Oil_India_ExtraDocument-GCO0449P23.pdf
-
Document-2
721.3 kBOil_India_ExtraDoc...Oil_India_ExtraDocument-GCO0449P23.pdf
Latest Corrigendum List
| # | Corrigendum Title | Corrigendum Type |
|---|---|---|
| 1 | Extension of Date for submission of Tender 13 | Date |
BOQ Items Total Items : 5 | Total Qty : 3
| # | Item | Quantity | Units |
|---|---|---|---|
| 1 | Providing/fabrication/replacement of old MIV seal of unit-1 with new:--- | ||
| 2 | Removal of old MIV Rubber Seal and providing/fabrication/replacement of new MIV seal by fixing of seal mentioned of MIV of Unit No. I at 2x2.25MW BAP Kafnoo Power House along with final testing and commissioning of above work in the presence of EIC complete in all respect with specification of material as follows: Seal Material: Rubber,OD: 2130mm, Thickness: 25mm, Sp. No. 5-552, V-170-1-9-200 . Scope of Work: 1. Removal of Old MIV Rubber Seal: Safely remove the existing rubber seal from the MIV.Ensure no damage is caused to the valve or other components during removal. 2. Fabrication/Replacement of MIV Seal: Fabricate a new MIV seal based on the provided specifications Seal specifications: Seal Material: Rubber Outer Diameter (OD): 2130mm Thickness: 25mm Specification Number (Sp. No.): 5-552 V-170-1-9-200: Likely a reference to the exact material or product code. 3. Installation of the New Seal: o Install the newly fabricated rubber seal onto the MIV in accordance with manufacturer guidelines and the system's requirements. o Ensure proper alignment and fit of the seal to avoid leaks and ensure long-term operation. 4. Final Testing and Commissioning: o Perform testing of the MIV with the new seal to ensure proper sealing, operation, and function. o Conduct the tests in the presence of the Engineer-in-Charge (EIC) to confirm that all work is completed per the specifications and quality standards. ( Note: See uploaded additional documents i.e. Complete job descriptions for complete detail of the job) | 1.000 | Job |
| 3 | Dismantling, Overhauling, Alignment, Re-installation and Commissioning of Gate Valve of Size 850 mm Dia. of Unit-1 | ||
| 4 | a) Dismantling of the existing damaged penstock gate valve of size 33.46 (850 mm) by means of welding, cutting, turning, grinding, etc. b) Cleaning and clearing of the seat, grooves and travel way of the penstock gate valve system. c) Repairing the eroded surface inside the body of the valve by turning and rebuilding the same with cast steel welding. d) Reassembling the valve after replacement of the wedge ring set, seal ring set, valve spindle, gland packing and all H.T. nuts, bolts, studs, washers and rubber gasket packing. e) Replacement of all damaged and rusted studs and nuts of size L = 158 mm and Dia. 19 mm with new superior quality studs and nuts. f) Greasing of the gear box of the gate valve. g) Painting of the complete gate valve body with two coats of silver paint of approved shade, as approved by the Site In-charge, to avoid rusting. h) Final assembly, installation, alignment, testing and successful commissioning of the above system complete in all respects to the entire satisfaction of the Engineer-in-Charge. | 1.000 | Job |
| 5 | Repair/Replacement of the sealing compound heat exchanger of Unit-1. Repair/ replacement of the sealing compound of the heat exchanger to prevent oil leakage. Replacement of damaged gaskets, nuts, bolts, and other necessary components shall also be carried out to restore the system to its proper operating condition. After completing the repair and replacement work, the heat exchanger will be reassembled and properly installed. Necessary alignment will be done to ensure smooth and efficient operation. The system will then be thoroughly tested to check for leakage and performance. Finally, successful commissioning of the heat exchanger will be carried out, complete in all respects, to the entire satisfaction of the Engineer-in-Charge. | 1.000 | Job |
Purchase Access To Download Selected Documents
₹ 200
Select this PlanFor a one-time fee, you get unrestricted access to all documents and for a minimum of one year.
UNLIMITED
DOWNLOAD
Select this Plan
₹ 7000
Plan
Standard Plane
Day/Month
Standard Plane
Sales: +91 7383 93 4054