Corrigendum Construction Of , Deoria - Tender Details
Explore tender information for Corrigendum Construction Of in Deoria, including eligibility, deadlines, and bid specifics.
Public Works Department
Deoria, Uttar Pradesh, India
NTID 38838213
Opening Date : Thu 20th March, 2025
Closing Date : Thu 20th March, 2025
- ₹ 8639000.00
- NTID 38838213
Corrigendum : Construction Of Pandey Fulwaria To Bhaiya Fulwaria Road.
Documents
Get Complete Tender Details Now – Download the Document!
Buy This Document-
721.3 kBOil_India_ExtraDoc...Oil_India_ExtraDocument-GCO0449P23.pdf
-
721.3 kBOil_India_ExtraDoc...Oil_India_ExtraDocument-GCO0449P23.pdf
Costs
-
EMD
632000.00 -
Document Cost
2950.00 -
Estimated Cost
8639000.00
BOQ Items Total Items : 13 | Total Qty : 26130.45
# | Item | Quantity | Units |
---|---|---|---|
1 | Earth work in cutting or embankment in ordinary soil loam, clay or sand in patries on both side of road including ramming dressing required to proper completion of work including all labourT&P etc . as per S.I. NO. 253 | 5650 | cum |
2 | Granular Sub-Base with Coarse Graded Material (Table:- 400, 1) (A) By Mix in Place Method Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method at OMC, and compacting with smooth wheel roller to achieve the desired density, complete as per MORD Technical Speicification Clause 401 For Gradingh 1 Material | 403.00 | cum |
3 | cement @ 2%opc cement treated subbase providing ,laying and spreding materails on prepared sub grade ,adding cement @2% opc by weight to the spread materials manuaally ,mixing in place with rotavator and compacting with the road roller at omc to achive the desired unconfined compressive strength and to form a layer of sub base. | 320.00 | cum |
4 | cement treated Base 4% cement opc WBM G-3 Providing laying and spreading materials on a prepared sub base, cement opc @ 4% by weight to the spread Material manually, mixing in place withh rotavator and compressive strenght and to form a layer of base. | 525.00 | cum |
5 | Providing and applying tack coat with bitumen emulsion using emulsion pressure distributor at the rate of 0.35 kg per sqm on the prepared bituminous granular surface cleaned with mechanical broom. | 6000.00 | sqm |

Purchase Access To Download Selected Documents
₹ 200
Select this Plan

For a one-time fee, you get unrestricted access to all documents and for a minimum of one year.
UNLIMITED
DOWNLOAD
Select this Plan
₹ 7000
Plan
Standard Plane
Day/Month
Standard Plane
Sales: +91 7383 93 4054