Inquiry NowConstruction Of Flood Protec in Karjat - Complete Tender Details
Find eligibility criteria, important deadlines, bidding requirements, and download official documents for " Construction Of Flood Protec" in Karjat, India.
PANCHAYAT SAMITI
Karjat, Maharashtra, India
NTID 42917963
- Opening Date : Mon 1st December, 2025
- Closing Date : Fri 28th November, 2025
- ₹ 1499219.00
- NTID 42917963
Tender Description
Documents
Get Complete Tender Details Now - Download the Document!
Download Now – Only ₹200-
Document-1
721.3 kBOil_India_ExtraDoc...Oil_India_ExtraDocument-GCO0449P23.pdf
-
Document-2
721.3 kBOil_India_ExtraDoc...Oil_India_ExtraDocument-GCO0449P23.pdf
Costs
-
EMD
Refer Documents -
Document Cost
1180.00 -
Estimated Cost
1499219.00
BOQ Items Total Items : 11 | Total Qty : 1247459.5285817
| # | Item | Quantity | Units |
|---|---|---|---|
| 1 | Item No. 1:-Cleaning grass and removal of rubbish up to a distance of 50 meters outside the periphery of the area as directed. | 700 | SQM |
| 2 | Item No.2 Providing and fixing 25mm diameter steel anchor dowel in hard rock including drilling hole of 32 mm diameter up to 0.75 mtrs depth, placing the dowel in position and effectively grouting the hole with CM 1:1 proportion etc. complete. | 152 | CUM |
| 3 | Item No. 3: Providing and laying in situ cement concrete of grade M-25 of trap / granite / gneiss / quartzite / graded metal for RCC works of gallery, sluice, spillway crest, spillway downstream face, energy dissipating structures, intake structures, training walls, piers, abutments, slab etc. with Concrete Mixer including shuttering and scaffolding, placing, compacting, curing with an initial lead of 1 km and all lifts etc. complete as directed. | 92.25 | CUM |
| 4 | Item No.: 4 Providing and laying weep holes of 80 mm dai. AC/PVC pipe as per drawing for Walls Including cost of all material and labour etc.complete | 31.5 | CUM |
| 5 | Item No.5:-Providing & laying in position TOR steel reinforcement including Cutting bending binding including cost of reinforcement binding wire etc complete with a lead of 50 m & lift of 1.50 m | 2.77 | CUM |
Purchase Access To Download Selected Documents
₹ 200
Select this PlanFor a one-time fee, you get unrestricted access to all documents and for a minimum of one year.
UNLIMITED
DOWNLOAD
Select this Plan
₹ 7000
Plan
Standard Plane
Day/Month
Standard Plane
Sales: +91 7383 93 4054